Construction Photos Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11
Page 12 Page 13 Page 14
See detailed
construction photo-journal at www.ConcreteCottage.com
|
 |
 |
| Late Sept 2007---Grouting has
begun. We are grouting the seams in the blocks before they are
backfilled with concrete. This keeps us from having seepage and a
lot of clean-up from the back-fill mixture. The pale blue in the cavity
of the blocks is the insulating foam. |
|

|
I made a little video of Don placing a
block. Mike is operating the crane and they are communicating
closely.
Watch Video
|
|
We do a good bit of cutting.
We are adapting blocks for this project that were originally poured for
a house in North Mississippi that was not built. The ends of corner blocks are cut out so the
back-fill concrete will flow thru them and provide a very strong
structure. |
 |
|

|

|
| The floor of the garage will
be poured after the first two courses of blocks are in place and they
will act as the forms for the floor. |
| Beautiful weather has made
things very pleasant on this property. Fall is the absolute best down
here. |
|

|
 |
|
More
Detailed Construction Photos |
|
|